Draft
Mission Planning
(~
15 Days/1 Month before Move)
 |
Implement
Customer Move/Transportation Plan. |
 |
Update
Payload Weight and CG. |
 |
Review
Lift Plans/Safety Procedures and Drawings (Super Guppy Shipping
Fixture, Flat Bed Trailers and Cargo Lift Trailers). |
|
Final
Mission Planning
(~
1/2 Weeks before Move)
 |
Review
Mission Directive sent from Customer Mission Planners. |
 |
Final
Briefing via Tele-con/Video Conference with Customer Counterparts. |
 |
Final
Review of Transportation Plan/Safety Procedures. |
 |
Final
Inputs/Comments between Loadmasters and Customer. |
 |
Payload
Data Confirmed. |
 |
Update
Line Items/Tasks to be performed at Onload/Offload Locations. |
 |
Mission
Movement Plan completed and signed off between Loadmasters |
 |
and
Customer. |
|
Mission Movement
 |
Movement
Coordination Loadmasters/Customer. |
 |
Run
Transportation Movement Control Center (TMCC) from JSC. |
 |
Ground
Support Equipment (Cranes, Aircraft, Load Cells, Cargo Loaders, etc.). |
 |
Integration
Payload/Super Guppy Shipping Fixture (SGSF), Weight and CG’s. |
 |
Quality
Control during Lifts/Movements of Flight Hardware. |
 |
Convoy
of Flight Hardware from Customer Facilities to Airport Facilities |
 |
Joint
Safety Briefings for Critical Lifts of Flight Hardware. |
 |
Joint
Sign Off of Procedures during Critical Lifts. |
|
In Flight Duties
 |
Super
Guppy Weight & Balance Authority. |
 |
Environmental
Control Systems (ECS) Operations and Monitoring. |
 |
Coordinates
Onload/Offload Operations with AOD Team Members. |
|
Mission
Debrief
(~
2 Weeks/1 Month after Move)
 |
Review
of the Previous Mission with Customer. |
 |
Safety
Concerns/Lessons Learned |
|